Saturday, 13 February 2016

Ready for the Kitchen & Bathroom Issues

Just in time, the living room and kitchen space is complete and has a day to dry ready for the kitchen to be fitted on 15th.



Unfortunately the main bathroom upstairs is not progressing so quickly. We discovered that the wall at the back of the shower is not included in the original offer so BBB had to construct this.


Also, the plumbers that fitted the ventilation system placed the air pipes where the bath will go so there are problems getting the bath feet in around these, and the bath can't be set as deeply in to the floor as we originally wanted.





1 comment:

  1. Automation can reduce down on this labor time cost however is just possible when excessive portions are required. 3ERP offers one-stop rapid prototyping services & low volume manufacturing services. With years oisture wicking underwear of producing experience, our consultants offer the best answer for all your rapid manufacturing wants. Learn Sheet metal design, processes and practical design issues together with Design tasks...

    ReplyDelete